Approved
27 Sep 2021 — 30 Sep 2022

Temporary Road Closure - Awatea Place and Parkers Road

Applicant: Hunter Civil
Location: Awatea Place – Full length
Parkers Road – Between 120 and 124 Parkers Road
Date and time of scheduled closure: Wednesday 27 September 2021 to Friday 30 September 2022. Closed all day and all night.
Event: The closure is for the Awatea Place Wastewater Pump Station Project. Work involves installing new wastewater pipes and manholes in the road.  
Awatea Place residents have been contacted about temporary access, which will be available via Parkers Road, with temporary parking provided within Nelson Airport Land.

Approved
19 Jan 2022 — 24 Nov 2022

Temporary Road Closure - Hastings Street

Applicant: Tasman Civil
Locations: Hastings Street
Date and time of scheduled closure: 7:00 am Tuesday 18 January to 8:00 pm Thursday 24 November 2022. Closed all day and all night.
The closure is for a stormwater upgrade.
There will be no on-street parking permitted during the closure but there will be some limited parking provided for residents in Pioneer park.
Vehicle access to the properties will be maintained except while works are directly outside properties.
Pedestrian access to the properties will be provided at all times for residents.
The footpath on Washington Road will be closed but pedestrians will be detoured using pathways in Pioneer Park.
Couriers and home help will need to use the limited parking provided at Pioneer Park while there is no access.
Rubbish bins are to be placed outside properties by 7:00 am as usual. We will make provisions to assist the collectors with picking them up and returning them to the properties.

Approved
14 Feb 2022 — 24 Nov 2022

Temporary Road Closure - Pioneer Crescent

Applicant: Tasman Civil
Locations: Pioneer Crescent
Date and time of scheduled closure: 7:00 am Monday 14 February to 8:00 pm Thursday 24 November 2022. Closed all day and all night.
The closure is for a stormwater upgrade.
Note: Hastings Street will remain closed for the same duration listed above (as previously advertised and approved)
There will be no on-street parking permitted during the closure but there will be some limited parking provided for residents in Pioneer Park.
Vehicle access to the properties will be maintained except while works are in the Pioneer/Hastings intersection.
Pedestrian access to the properties will be provided at all times for residents.
The footpath on Washington Road will be closed but pedestrians will be detoured using pathways in Pioneer Park.
Couriers and home help will need to use the limited parking provided at Pioneer Park while there is no access.
Rubbish bins are to be placed outside properties by 7:00 am as usual. We will make provisions to assist the collectors with picking them up and returning them to the properties.

Cancelled
8 Mar 2022 — 29 Jul 2022

Temporary Road Closure - Brougham Street and Scotland Street

Applicant: Nelson Marlborough Traffic Management
Locations: Brougham Street – between Scotland Street and Collingwood Street
Scotland Street – between Brougham Street and Seymour Ave
Date and time of scheduled closure: Tuesday 8 March to Friday 29 July 2022. Closed between 9.00am and 3.30pm.
The closure is for the connection of stormwater services.    
Vehicle access to residents, rubbish collection vehicles and home help will be available where possible, however, delays are likely. Pedestrian access will be provided.
Some on street parking will still be available for residents.
Rubbish and recycling bins will be collected as normal.

Approved
2 May 2022 — 8 Aug 2022

Temporary Road Closure - Princes Drive - End Cul-de-sac

Applicant: Fulton Hogan

Location: Princes Drive – end cul-de-sac

Date and time of scheduled closure: Monday 2 May to Monday 8 August 2022.  Closed all day and all night.  Work hours between 6.00am and 6.00pm daily.

The closure is for a watermain replacement. 

Resident access is available. 

Rubbish and recycling bins will be collected as normal.

 

 

Approved
3 May 2022 — 25 May 2022

Temporary Road Closure - Vickerman Street

Applicant: Downer

Locations: Vickerman Street – between Haven Road and Wildman Ave

Date and time of scheduled closure: 7.00am Tuesday 3 May to 7.00pm Wednesday 25 May 2022. Closed all day and all night.

The closure is for trenching and laying storm water pipes.  This is a part of the Stormwater Upgrade Project.

Vehicle access to businesses will be available where possible, rubbish collection and recycling bins will be collected as normal.  There will be a detour in place.

Pedestrian access will be provided.

Approved
5 May 2022 — 30 Jun 2022

Temporary Road Closure - Karaka Street

Applicant: Higgins

Locations: Karaka Street – Polstead Road to Titoki Street

Date and time of scheduled closure: 7.00am Monday 9 May to 6.00pm Thursday 30 June 2022.  Closed all day and all night.

The closure is for footpath renewal, driveway renewals and kerb and channel maintenance.

Vehicle access to residents, rubbish collection and recycling bins will be collected as normal and home help will be available where possible, however, delays are likely.

Pedestrian access will be provided.

Approved
10 May 2022 — 17 May 2022

Temporary Road Closure - Russell Street

Applicant: Nelmac

Locations: Russell Street – between Washington Road and Retone Street

Date and time of scheduled closure: Tuesday 10 May 2022.  Closed between 7.00am to 6.00pm

Contingency date and time: Tuesday 17 May 2022.  Closed between 7.00am to 6.00pm.

The closure is for tree maintenance.

Vehicle access to residents will be available where possible, and rubbish collection and recycling bins will be collected as normal. 

Pedestrian access will be provided.

Approved
16 May 2022 — 27 May 2022

Temporary Road Closure - Athol Street between number 6 and number 12

Applicant: Downer

Location: Athol Street – between number 6 and number 12

Date and time of scheduled closure: 9.00 am Monday 16 May to 6.00 pm Friday 27 May 2022.  Closed all day and all night.

The closure is for installing a stormwater crossing and upgrading the kerb and channel. 

Vehicle access will be unavailable. Access for properties past number 12 will be via Seafield Terrace/northern end of Athol Street.

Rubbish collection and recycling bins will be collected as normal. 

Pedestrian access will be provided.

Proposed
18 May 2022 — 25 May 2022

Temporary Road Closure - Shelbourne Street - full length

Applicant: Nelmac

Locations: Shelbourne Street – full length

Date and time of scheduled closure: Wednesday 18 May 2022.  Closed between 9.00am and 2.00pm.

Contingency date and time: Wednesday 25 May 2022.  Closed between 9.00am and 2.00pm.

The closure is for stormwater flushing that will be in the middle of the road. 

Vehicle access to residents and home help will be available via entrance from Bronte Street. Rubbish and recycling will be collected as normal.